March 1
Attending: Eric and Jay from NERSC; users Andrei, Jeff P., Jeff A., Doug O.
Utilization: Cluster continues to be filled to capacity.
Outages: There was an interacxtive reboot; eliza5 maintenance; work on pdsfdtn1 tomorrow; eliza12/13 to go away Friday
Procurements: New hardware expanded eliza5 by 100%.
Project Accounts: Getting restarted - Jay to talk to security.
Some LDAP problem were occurring during this meeting...
ATLAS grid: seems to be working with new entries in the grid-mapfile
STAR/ALICE grid: Some problems w the ALICE SE; setting up test w/vo box to send jobs to other gatekeepers
Andrei on cvmfs: Expect to see more usage, they are no longer using /common; working on getting it on all nodes; need it on debug and pdsfdtn1 - Jay to look
Jay: we want to put memory limits on the interactive nodes - probably set to 2GB...
The debug node is dual socket 8 core, 2GB/core so we could consider an upgrade if it starts getting heavier use
Jeff: fixing cron on ALICE servers - somehow Jeff's access no longer works (?)