April 26
Attending: Eric, Jay, Jeff P., Jeff A., Marjorie, Andrei
Clusture Utilization: Filled to capacity.
- eliza18 maintenance has been completed.
-The new website has gone live now.
Procurements: Putting in new dayabay storage - should be done by the end of the week.
- Need to do network work for the new ALICE storage - this will take a couple weeks at least.
Outage/Incidents: A downtime will be needed to move to new home - will take 9 hours or less (?) so will allocate a full day, tentatively scheduled for May 25.
Grid Issues: Have received response from RT and learned that ATLAS grid transfers were failing due to a timeout while doing checksum. Jay put in a different way to do the checksum and will do some testing of i/o.
- ATLAS has completed their cleanup of /common.