October 30 Power Upgrade
Beginning Monday, October 30, there will be a major power upgrade in the NERSC
machine room. This page documents the planned schedule for taking down the
various systems and subsequently returning them to service. All times are
Pacific Standard Time.
All systems must be powered down so work can begin by 11:00. User access to
most NERSC system will be terminated at 04:00. The outage is
expected to last between 36 and 48 hours. Once the electrical contractor
has restored power, NERSC staff will begin the process of bringing the Center
back into production. Compute systems that mount NGF will not return to
service until NGF is operational.
For status updates, including estimates of the return
to production of NERSC services, please see the
Message of the Day.
Network Access
-
All network access to NERSC systems will be disabled at 09:15. Network
connectivity will resume approximately 30 minutes after power is restored.
There may be a few 30-second network interruptions for approximately 4
hours after power is restored.
Seaborg
-
A LoadLeveler reservation will be used to guarantee that all batch jobs have
completed by 04:00. Interactive logins and processes will also be killed at
04:00.
Seaborg will return to full service approximately 4 hours after NGF returns
to service.
Jacquard
-
A PBS reservation will be used to guarantee that all batch jobs have
completed by 04:00. Interactive logins and processes will also be killed at 04:00.
Jacquard will return to full service approximately 2 hours after NGF returns
to service.
Bassi
-
A LoadLeveler reservation will be used to guarantee that all batch jobs have
completed by 04:00. Interactive logins and processes will also be killed at 04:00.
Bassi will return to full service approximately 2 hours after NGF returns
to service.
DaVinci
-
DaVinci will be taken down at 04:00. It will return to service approximately
1 hour after NGF returns to service.
PDSF
-
PDSF will be removed from service at 04:00; all batch and interactive processes
will be killed. The system will return to service approximately 6 hours after
NGF returns to service.
HPSS
-
The two HPSS systems (archive.nersc.gov and hpss.nersc.gov) will become
unavailable at 04:00. The NERSC AFS cell also will be taken down at 04:00.
All NERSC storage systems will be returned to service approximately 2 hours
after power is restored.
NGF
-
NGF will be powered down once all the systems that mount it have been
removed from service. It will return to service approximately 4 hours
after power is restored to the Center.
Web Site
-
The NERSC website will remain available during the outage, with reduced
functionality. In particular, pages that require password authentication
(NIM, batch queue status, completed jobs, etc) will not be available.
There will be brief interruptions in web availability shortly before and
after the power outage.
For status updates, including estimates of the return
to production of NERSC services, please see the
Message of the Day.
NIM
-
NIM will become unavailable beginning at 06:30, and will return to service
approximately 1 hour after power is restored.
CVS Server
-
The NERSC CVS server will be removed from service at 06:30, and will return
to service approximately 1 hour after power is restored.
License Servers
-
The remote license servers will be removed from service at 06:30, and will
return to service approximately 30 minutes after power is restored. During
the outage, remote applications such as IDL that depend on the NERSC license
servers will be unavailable.
|